Access scaffold to bridge steelwork for repairs and blast & paint works. A beamed crash deck was provided for the full length of the bridge so that the line could remain open whilst works continued above. The design also included a mobile overhead crane for lifting and placement of new steelwork. The crash deck was subjected to full scale (off-site) testing to ensure it's suitability for the project.
Scaffold during construction, access towers and first lift in place.
Project name:
Brotherton Bridge - River Aire
Location:
Brotherton Bridge, River Aire, Ferrybridge/Brotherton.
Type of Scaffold:
Access scaffold, crash deck and overhead crane.
Scaffolding Contractor:
SYS
Client:
May Gurney Rail
Our Client:
Mott McDonald
Date of Works:
May to November 2002