Scaffold Design Experience
Scaffold Design Expertise
REAL Scaffold Design Knowledge
A long running design project for May Gurney Rail on this Grade I listed structure. The design work was complex in places and included many types and forms of scaffold. These included an underdeck drop access scaffold for steelwork repair and timber deck replacement, access scaffolds to structural steelwork and drop-tested public protection decks. The design project was passed to Pyeroy inhouse design team in Spring 2006 and since then we have been acting as independent checkers on behalf of May Gurney Rail.
This photograph shows scaffold during erection at the Southern entrance to the bridge (21st March 2005).
Project name:
High Level Bridge, Newcastle-Upon-Tyne
Location:
Newcastle-Upon-Tyne.
Type of Scaffold:
Various
Scaffolding Contractor:
Pyeroy
Client:
Network Rail
Our Client:
May Gurney Rail
Date of Works:
2004 to Spring 2006